How much does a general contractor charge in Florida?What are the common ways a general contractor charges?What does a general contractor’s price include?How much deposit can a Florida contractor ask for?What must a Florida residential contract include?How do I compare general contractor bids?Frequently asked questionsKey takeaways
- There is no public rate card or standard markup: the price is the cost of the work plus overhead and profit, and the contract type decides who carries overruns.
- Bids come in three main shapes: fixed price, cost-plus (actual costs plus a fee) and cost-plus with a cap. The model decides who pays when costs run over.
- Florida’s s. 489.126 sets deadlines, not a deposit cap: if the first payment tops 10 percent of the price, the contractor must apply for permits within 30 days and start within 90 days after they issue.
- Residential contracts above $2,500 generally need the recovery fund and construction lien notices, and every proposal must show the contractor’s license number.
- Compare bids on one written scope, with allowances, exclusions, payments and change orders side by side.

How much does a general contractor charge in Florida?
There is no single Florida rate. A general contractor charges the cost of the work (labor, materials, subcontractors) plus overhead and profit, and how those appear on your bill depends on the contract. BuildingAdvisor wrote in 2016 that there is no industry standard for markup, which varies by job type, region and market.
The most current benchmark is NAHB’s 2026 Remodelers’ Cost of Doing Business Study: for 2024, remodelers averaged a 29.9% gross profit margin and a 6.3% net profit margin. NAHB’s summary does not define either margin, so treat them as industry context, not a markup or a price check.
Margin and markup differ. A margin is a share of the price you pay; a markup is a share of the contractor’s cost. A 25 percent markup on $100 of cost makes a $125 price, a 20 percent margin. Ask which one a quoted percentage is.
What are the common ways a general contractor charges?
Most residential bids fall into three structures: fixed price, cost-plus, and cost-plus with a cap. The difference is who pays when costs run over.
| Model | How you pay | Who carries overruns | Watch for |
|---|---|---|---|
| Fixed price | A set total for a defined scope. Per Consumer Reports (2016), it covers labor, materials, profit and a contingency cushion. | Mostly the contractor, for foreseeable overruns | Vague scope, low allowances, cut corners |
| Cost-plus | Actual costs plus a fee or percentage; sometimes called time-and-materials | The homeowner; no contingency is built in | Open-ended totals and billing you must track |
| Cost-plus with a cap | Actual costs plus a fee, up to a guaranteed maximum or not-to-exceed price | The cap limits what you can be charged | What can raise the cap; whether savings are shared |
BuildingAdvisor’s author prefers a fixed price in most cases, if the scope will not change much after work starts, and says cost-plus can be a necessity when many unknowns exist. Consumer Reports notes that a cost-plus owner keeps any savings if the job finishes under budget. Under cost-plus, ask for a cap and itemized billing.
Two terms appear in every model. Allowances are placeholder amounts for items not yet chosen, and pricier picks raise the price. Change orders record scope changes, and some contractors charge an administrative fee for each. Ask about both before you sign.
What does a general contractor’s price include?
A complete price covers the written scope: labor, materials, subcontractors, and the contractor’s overhead and profit. Anything the scope leaves out is not in the price.
Check permits and inspections (who applies and who pays the fees), demolition and disposal, what each allowance buys, exclusions such as appliances or backsplash, and whether a fixed price includes a contingency and who keeps the unused part.
Published cost ranges are in the kitchen remodel cost guide and budget rules of thumb; they are third-party estimates, not quotes. A single “turnkey” number should still be itemized; see turnkey kitchen remodeling for what that approach covers.
How much deposit can a Florida contractor ask for?
Section 489.126 sets deadlines, not a deposit cap. If the first payment on residential work exceeds 10 percent of the contract price, the contractor must apply for needed permits within 30 days and start work within 90 days after they issue. Just cause, or your written agreement to a longer period, excuses the deadlines.
A contractor holding more than the value of the work performed may not go 90 days without doing any work, or the period the contract sets (s. 489.126(3)). If a contractor misses these deadlines, ask a Florida construction attorney or DBPR what you can do.
Local guidance goes further than the statute: Hillsborough County advises paying no more than 10 percent before work starts, and UF/IFAS suggests tying draws to percent complete.
What must a Florida residential contract include?
Florida requires specific notices and the contractor’s license number. Scope, schedule and payments are whatever you negotiate, so write them down.
- License number on every offer of services, proposal, bid and contract (s. 489.119(5)(b)).
- Recovery Fund and lien notices in residential contracts above $2,500, subject to the conditions in the statutes. The lien notice warns that unpaid subcontractors and suppliers can claim against your property, and advises requiring written lien releases before payment (ss. 489.1425, 713.015).
- Final payment affidavit. The contractor must give you a sworn affidavit that lienors who served notice are paid, or listing those who are not. The owner holds final payment until it arrives (s. 713.06(3)(d)).
- Scope, dates and payments. Hillsborough County says a contract should cover scope, start date, estimated duration and payment schedule. UF/IFAS adds a definition of completion, a warranty and separate change orders.
A federal rule, not a Florida contract requirement, can also matter: the FTC’s Cooling-Off Rule gives some buyers until midnight of the third business day to cancel certain sales made in the home, but it does not apply if you sign at the contractor’s permanent place of business, and emergencies and repair visits you requested are excluded. Ask the contractor and an attorney whether it applies to your contract (FTC page).
The $2,500 line is not the $7,500 or $15,000 figure in Florida’s permit rules; our guide to contractor vs. general contractor in Florida puts all three in one table.
How do I compare general contractor bids?
Put every bid on the same scope sheet, name each pricing model, and compare what is included before you compare totals.
- 01
Match the scope
Give every contractor the same layout, selections and appliance list, and list what each allowance buys. A lower total often means a smaller scope.
- 02
Name the model
Fixed, cost-plus or capped? For cost-plus, ask what the fee is calculated on and what the cap is.
- 03
Check the payments
Compare each deposit and milestone with s. 489.126.
- 04
Ask about gaps
Ask contractors to explain large differences, as the FTC advises. UF/IFAS warns against treating the lowest price as the best value.
- 05
Verify before you sign
Confirm the license and insurance with our guide to checking a Florida contractor license, then use the questions in how to choose a kitchen remodeler.

Frequently asked questions
How much does a general contractor charge in Florida?
There is no single rate. The price covers the cost of the work plus overhead and profit, and depends on contract type and scope. NAHB reports 2024 averages of a 29.9% gross and 6.3% net profit margin for remodelers; these are margins, not a markup or a quote.
How much do most general contractors charge?
There is no single standard markup, and no official source sets a typical percentage. Compare the contract model and the written scope instead.
Is a fixed-price or cost-plus contract better?
Neither wins every time. A fixed price gives a predictable total if the scope will not change much after work starts. Cost-plus can suit work with many unknowns, but the owner carries overrun risk unless the contract has a cap.
How much can a Florida contractor ask for as a deposit?
Section 489.126 sets no cap. If the first payment exceeds 10 percent of the price, permit and start deadlines apply unless there is just cause or you agree otherwise in writing. Hillsborough County advises paying no more than 10 percent before work starts.
Is it cheaper to hire a general contractor or manage the trades myself?
It depends. Managing the trades yourself avoids paying a contractor to coordinate but puts scheduling, permits and risk on you. Florida allows owner-builders under conditions (s. 489.103(7)); ask your building department what applies to your property. Our permit guide covers the details for Tampa and Hillsborough County.
Keep reading
Contractor vs general contractor in FloridaIn Florida, “general contractor” is one license category inside the broader legal term “contractor.” Here is what each license allows, what needs no…Read more
Kitchen remodel cost in Tampa Bay: what published estimates sayThe 2025 Cost vs. Value report prices three standardized Sarasota kitchen jobs from about $28,600 to about $161,200; other published sources report…Read more
Is $30,000 enough for a kitchen remodel in Florida?Sometimes. In published estimates, $30,000 covers a minor refresh of a typical kitchen but falls well short of a full remodel with new cabinets…Read moreSources
- NAHB (April 2026): Home remodeling profit margin, from the 2026 Remodelers’ Cost of Doing Business Study
- Consumer Reports (2016): Know what type of remodeling contract you are signing
- BuildingAdvisor (2014): Allowances, what’s fair, and fixed-price vs. cost-plus contracts
- BuildingAdvisor (2016): Cost-plus, how much markup?
- UF/IFAS Extension: How to Hire and Manage Residential Contractors (FCS3318)
- Hillsborough County: Selecting a Contractor in Hillsborough County
- FTC Consumer Advice: How To Avoid a Home Improvement Scam
- FTC Consumer Advice: Buyer’s Remorse, the FTC’s Cooling-Off Rule may help
- Florida Statutes 2026, s. 489.126 (moneys received by contractors)
- Florida Statutes 2026, s. 489.119 (license number in proposals, bids and contracts)
- Florida Statutes 2026, s. 489.1425 (recovery fund notice in contracts)
- Florida Statutes 2026, s. 713.015 (mandatory lien notice in direct contracts)
- Florida Statutes 2026, s. 713.06 (final payment affidavit; owner’s retention of final payment)
- Florida Statutes 2026, s. 489.103 (exemptions; owner-builder)